In January 2019, the Town of Argyle issued $2,750,000 for a large-scale road improvement project to include microsurfacing approximately 5.6 miles of roads, repair/maintain 2.75 miles of roads with an asphalt overlay and reconstruct approximately 2 miles of roads throughout the town. Below is an estimated timeline of the project along with draft documents associated with the project. For further information, please reach out the Public Works Director Troy Norton.
Key Dates (updated 11/26/2019):
April 4, 2019 | Public Meeting on Draft Documents, Argyle Town Hall, 6p-8p |
May 2019 | Microsurfacing Project Begins |
June 2019 | Bid Part 1 and Part 2 of Project
|
July 2, 2019 | Town Council Awarded Part 1 and Part 2 Contracts
|
Reference schedule here
| Part 2 Construction Underway (Stonecrest, Sam Davis and Gibbons)
|
Reference schedule here
| Part 1 Construction Underway (Whispering Trails and Harpole) |